Dynamic Project Scheduling and Progress Monitoring of Engineering Phase in FPSO Conversion Project with Fuzzy Method
DOI:
https://doi.org/10.11113/oiji2021.9n2.155Keywords:
Fuzzy Linguistic, Fuzzy Membership Function, Progress Measurement, Resource Management, RegressionAbstract
Project scheduling and progress measurement for engineering phase of floating production storage and offloading (FPSO) conversion project always faces uncertainties which frequently require re- scheduling when variance between plan progress and actual progress is too large. This research studies the dynamic nature of project scheduling of engineering phase for an FPSO conversion project where correlation of variables of number of deliverables in Master Deliverable Register (MDR), Manhours (MHR) and project duration against project progress are analysed using the regression method. The projection of these correlations against project progress are results to a Three-Dimensional surface plot of project progress at a chosen control variable of either MDR, MHR or duration.